HYDROENERGY JIJI MULEMBWE


Overview

  • Reference: P-BI-FA0-100
  • Approval date: 23/06/2014
  • Start date: 13/01/2015
  • Appraisal Date: 07/01/2014
  • Status: OngoingOnGo
  • Implementing Agency: MINISTERE DE L'ENERGIE ET DES MINES
  • Location: JIJI ET MULEMBWE

Description

Composante I: Production hydro


Key contacts

AKITANI Elise Massan - ONEC2


Costs

Finance source Amount
GovernmentUAC 10,930,000
Co-financierUAC 165,290,000
TotalUAC 176,220,000