Projet de route Kumba-Mamfe


Overview

  • Reference: P-CM-DB0-011
  • Approval date: 21/11/2012
  • Start date: 07/11/2013
  • Appraisal Date: 20/07/2012
  • Status: OngoingOnGo
  • Implementing Agency: MINISTERE DES TRAVAUX PUBLICS
  • Location:

Description

Le Pr


Objectives

L'objectif global du projet est de contribuer


Rationale

Le pr


Benefits

Cette route qui traverse la deuxi


Key contacts

MBA Samuel - OITC1


Costs

Finance source Amount
ADFUAC 47,260,000
GovernmentUAC 29,570,000
Co-financierUAC 31,620,000
TotalUAC 108,450,000