TAKORADI II EXPANSION POWER PROJECT


Overview

  • Reference: P-GH-FD0-002
  • Approval date: 11/07/2012
  • Start date: 23/01/2013
  • Appraisal Date: 28/02/2011
  • Status: OngoingOnGo
  • Implementing Agency: TAKORADI INTERNATIONAL COMPANY LLC
  • Location: Ghana

Description

Expansion of the existing 220 MW single cycle gas/fuel oil power plant to 330 MW combined cycle at Takoradi in Western Ghana. The existing plant has been in operation since September 2000. The expansion will use 2 heat recovery steam generators placed in the exhaust path of the gas turbines and is scheduled to deliver power as early as third quarter of 2013.


Key contacts

DERBY Nanette Esi - OPSD4


Costs

Finance source Amount
ADBUSD 38,146,100
Co-financierUSD 234,598,512
DeltaUSD 272,744,612