La Gogue Water Supply Project


Aperçu

  • Référence: P-SC-EA0-004
  • Date d’approbation: 01/04/2015
  • Date de début: 10/11/2015
  • Date d'évaluation: 01/11/2014
  • Statut: En coursOnGo
  • Agence d'implémentation: WATER AUTHORITY PUBLIC UTILITIES CORPORATION
  • Emplacement: Mahe Island, Victoria

Justificatif

The unmet demand for Seychelles is estimated at 40% according to the WDP for 2010. The deficit will continue to increase if further investments are not made timely as recommended inhibiting the economic and social development of the country. It is therefore imperative that the priority activities in the WDP are implemented in a timely and orderly manner. The enhancement of storage at La Gogue dam reservoir is one such activity to ensure water security. The PUC has already embarked on smaller scale improvements to transfer water to the La Gogue dam reservoir. The Salazie and Mount Simpson transfer schemes (4500m3/day capacity) being implemented by the PUC with an outlay of SCR 35 million are typical examples of the efforts to increase availability of water resources. The benefit of such schemes will be much more enhanced with an increase in storage volume. The implementation of this scheme is therefore critical to enhance the capacity of water storage and provide water security to the main island. The storage enhancement scheme will also enable the improvement of the La Gogue distribution system. The WDP shows that the benefits of the new system over the long term is enormous in terms of improving efficiency of the system and reducing operation and maintenance costs. The improvement of the system will see the reduction of pumping stations and shorter distances along the distribution network thus resulting in better control of the residual chlorine contact, better pressure management and leak control. The technical justification described above provides the justification for carrying out the feasibility study and detail designs preparation in order to make the project ready for implementation.

The GOS approved the WDP in June 2011 and immediately embarked on the implementation of the recommendations of plan. The GOS further demonstrated its leadership and political commitment to the implementation of the WDP by organising a donors' conference on 13th September 2011 to mobilise support for the implementation of the WDP. The conference was successful and was attended by government officials, donors including AWF, EIB, BADEA, UNDP, Embassies and other stakeholders. Donors expressed their commitment to strengthen their collaboration with GOS for the implementation of the WDP.

The Bank's CSP gives prominence to infrastructure development vis-


Bénéfices

The WDP specifically recommends the immediate raising of the height of La Gogue Dam on a priority basis to increase the water storage capacity. According to previous studies and WDP, raising of the height of La Gogue dam by about 5m would alone increase the reliable yield by an average of 3,900m3/day. This additional resource is equivalent to about 50 days of water for the Islands representing 14% of water currently produced. The other alternative considered for storing water was the building of a new dam on the Grand Anse River. However this alternative was dropped due to the environmental concerns and engineering complexities. The raising of the La Gogue dam was therefore deemed the most attractive option due to the amount of fresh water storage to be achieved and the potential for transfer of water from adjacent surplus catchment. The raising of La Gogue dam is therefore a strategic water security enhancement scheme for Seychelles and there is need to further investigate this option to confirm the feasibility of the scheme.

The development of this scheme, if feasible, will further provide the possibility to improve the La Gogue distribution zone with the construction of La Gogue water supply treatment plant (gravity fed system) resulting in net cost saving over longer period from the present energy intensive distribution system in La Gogue area, thereby contributing to the mitigation of climate change. This region is considered to have intermittent supply due to problem of low pressure and long distances from the existing treatment plants at Hermitage and Le Niol. There are 12 pumping stations within this area with high energy costs. In order to reduce these constraints, a new system is proposed, namely the construction of a new treatment works at La Gogue providing supply directly to this distribution zone.


Contacts clés

MUTASA Christopher - OWAS2


Coûts

Source Montant
BADUSD 13.894.697
MICFUSD 1.200.000
GovernementUSD 2.694.627
DeltaUSD 4
TotalUSD 17.789.328