Mission date: From: 18.5.2020 To: 21.05.2020
Bothe the outcome and output are satisfactory at this stage, whereas there is a challenge and risk to the project, which is the wayleave and compensation payments on the transmission lines due the court cases and absentee PAPs
Mission date:
Ethiopia from: 20/05/2019 To: 20/05/2019
Kenya from: 27/05/2019 To: 31/05/2019
The three outcome indicators were not related to this IPR as they were more related to the Kenya part of the project
Mission date:
Ethiopia from: 09.12.2019 To: 13.12.2019
Kenya from: 02.12.2019 To: 06.12.2019
Bothe the outcome and output are satisfactory at this stage, whereas there is a challenge and risk to the project, which is the wayleave and compensation payments on the transmission lines due to...
Mission date: From: 17.05.2019 To: 17.05.2019
The two Outcome indicators are off-track but with the expected acceleration of the implementation of activities from Q4, 2019 all outcomes are expected to be achieved by the end of the Project.
Mission date: From 25/11/2019 To 29/11/2019
The development goal is to develop a domestic aquaculture subsector which serves as viable and inclusive business opportunity through enhanced production and productivity to improve the livelihoods of men and women beneficiaries along the...
Mission date: From 15/04/2019 To 18/04/2019
The project has made tremendous progress since it was signed. The full attainment of the DO will be achieved once outputs are generated.
Mission date: From 20/08/2018 To 25/08/2018
The project has completed and delivered the core outputs. The timely completion of infrastructure designs will allow for timely procurement of civil works under the main project.
23-Jun-2020
Zambia - Agriculture Productivity and Market Enhancement Project (APMEP) - IPR Décembre 2019
Mission date: From: 11 November 2019 To: 15 November 2019
The Project objectives are to contribute to economic growth and poverty reduction by ensuring food, income and nutrition security among beneficiaries.
Mission date: From 03.02.2020 To 10.02.2020
The overall implementation is currently slow; however, over 15 construction and rehabilitation contracts have been signed and implementation is expected to pick up steam in Q2, 2020 and maintain the trajectory in rest of 2020.