Contract Awards - Multinational - Road Safety Audit of the Preliminary and Detailed Designs of the Abidjan- Lagos Corridor Highway

12-Dec-2019
  1. Hold a pre-audit meeting with the ECOWAS Commission and other stakeholders to review project information available. The pre-audit meeting is to set the context for the Road Safety Audit by bringing together the staff of the Infrastructure Department on the ECOWAS Commission , the PIU, the Design Consultants, and the Road Safety Auditor to discuss the scope, objective of the audit and review all information available.
  2. Compilation of available road design texts and standards applicable by each Corridor Country or recommended by ECOWAS;
  3. Assist with the harmonization and validation of highway standards to be applied in the design of the highway
  4. Review of Design Reports and Drawings to gain insight into the project, identify preliminary areas of safety concern and prepare for the field visit.
  5. Undertake a field visit and inspect the project site, identify/verify and establish a clear understanding of safety concerns including locations with pedestrian traffic in relation to the documents reviewed and ensure that these safety concerns are adequately addressed in the design documents.............................