You are here

Chad - Telecommunications Infrastructure Rehabilitation Project - PPER

15-Jan-2014

This performance evaluation report concerns the Telecommunications Infrastructure Rehabilitation project (RIT), identified in 1981 on presentation of the emergency infrastructure rehabilitation programme for financing by the International Donor Community. The project was appraised in November 1986 and the corresponding ADF loan, for an amount of MUA 15.10 million, covering 90% of the project cost (MUA 9.847) and the entire foreign exchange cost, was approved on 18/12/98 and signed on 5/2/87. The Government of Chad financed 75.3% of the local costs, representing MUA 1.68. The works were estimated to take 39 months and the executing agency was ONPT.