Kenya - Timboroa Eldoret road rehabilitation project - Completion report of the project -PCR

03-Jul-2017

The project objectives are consistent with Government of Kenya’s long-term economic development strategy(Vision 2030)whose first five-year Medium Term Plan (MTP) for the period 2008-2012 had three overarching pillars,namely, economic, social and political, with foundations anchored on expansion of economic infrastructure. The project was also in accord with the main purpose of the Road Sector Investment Program (RSIP) 2010-2014 which is to provide good roads for a globally competitive and prosperous Kenya.