Malawi - Mzuzu-Nkhata Bay Road Rehabilitation Project - Appraisal Report

24-Jan-2020

Mzuzu-Nkhata Bay Road Rehabilitation Project will involve widening of the 46km road between the towns of Mzuzu and Nkhata Bay from the current 4.2m to 6.7m and construction of an asphalt concrete running surface with 1.5m sealed shoulders. The total project cost estimate is UA22.946 million, with the Bank contributing UA21.890 million (95%) and the Government of Malawi contributing UA1.056 million (5%). The project is planned to be implemented over a period of four years starting from 2013 to 2017. The project duration includes 12 months of design review, preparation of bidding documents and procurement of civil works, 24 months construction period, and 12 months defects liability period.