Mission date (if field mission):  From 29/07/2018 To 03/08/2018

The Output performance is on track and hence rated as satisfactory. The DO is expected to be realized in 9 months and hence the outcome indicators are expected to be fully reached in June 2019. The main project outcomes are the IWRM and Investment Plan adopted by the stakeholders and the mobilization of funds to finance downstream investments and the strengthening of water institutions to be able to manage water resources in accordance with the Water Resources in accordance with the Water Resources Management Plan.