P-GM-FA0-002

%

10-Oct-2019

Republic of the Gambia - The Gambia Electricity Access Project (GEAP) - Project Appraisal Reports

The Gambia Electricity Access Project’s ultimate objective is to increase the Gambian population's access to affordable and reliable electricity services. It will involve the construction of Medium and Low Voltage lines, erection of transformers and connection of customers in Lower River, North Bank, Central River, and West Coast regions. From the OMVG Energy Project’s two substations (Brikama and Soma), under physical implementation, the project will provide people (men and women) with electricity access and improve the performance of the National Water and Electricity Company (NAWEC) by...