ITOBE COAL POWER PROJECT


Overview

  • Reference: P-NG-FB0-001
  • Appraisal Date: 13/12/1901
  • Board Presentation: 02/11/2016
  • Status: PipelinePIPE
  • Implementing Agency: --
  • Location: NIGERIA

Description

Construction, operation and maintenance of a coal fired power plant, with total generation capacity of 1,200 MW (8 units x 150 MW) in Nigeria. Project scope includes the construction of the power plant, 16km transmission line from the plant to the existing Ajaokuta 330 kV substation, and the expansion of the substation to cater for the new connection load. The first phase will include the installation of 2 units x150 MW.


Key contacts

SHUNDO Kenji - PESD1


Estimated Cost

Amount
 1,238,469,000