KENYA - TANZANIA INTERCONNECTION (KENYA)


Overview

  • Reference: P-Z1-FA0-086
  • Approval date: 18/02/2015
  • Start date: 12/05/2016
  • Appraisal Date: 08/10/2014
  • Status: OngoingOnGo
  • Implementing Agency: KENYA ELECTRICITY TRANSMISSION CO. LTD
  • Location: Kenya

Key contacts

MUGUWA Andrew - RDGE1


Costs

Finance source Amount
ADFUAC 27,500,000
GovernmentUAC 5,100,000
TotalUAC 32,600,000