Rwanda - Muvumba Multipurpose Water Resources Development Program Phase 1 - P-RW-EA0-015 - ESIA Summary

15-jan-2020

Muvumba multipurpose dam project is a governmental project that intends to construct a dam of 30.5m high and will impound 35 million cubic meter of water in Karama, Gatunda and Rukomo sectors and will supply water for domestic use to Karangazi, Rwempasha and Nyagatare sectors. The dam will impound water to be used for domestic water supply, water for irrigation of 7380 ha (net command area) and water for 16 reservoirs for livestock watering production of annual annual energy of 5719 Mwh with installation capacity of 740 KW (370x2). It will also contribute to the flood control.