ID: P-ZW-FAB-001 Name: POWER SYS. REHAB. (ELEC. I) PROJEC Status: Closed Country: Zimbabwe
Sector: Power Approval date: 26-oct-1987 Task Manager: -, OINF3
Total cost: 149000000
Currency: UAC
Source(s) of financing
AfDB: 32770000
Cofinanced: 55980000
Government: 76040000
Implementing Agency: GOUVERNEMENT DU BURUNDI Location: Throughout the country

Objectives

1. Overall Objective: To rehabilitate power system of Zimbabwe ----------------- 2. Specific Objectives: Strengthening of transmission lines -------------------

Description

The project (ADB portion) comprises of construction of the following transmission lines. 1. 330 kV Alaska-Mutorashanga 2. 330 kV Tokwe-Traingle 3. 132 kV Mutorashanga-Bindura 4. 132 kV Seki-Dema 5. 330 kV Seki-Dema 6. 132 kV Haven-ZIMASCO 7. 132 kV Haven - Zisco, 8. 132 kV ZISCO-Ripple Creek 9. 330 kV In/Out Insukumani 10. 132 kV Insukumani-Pamula South

Benefits

ZESA.

Rational

1. Overall Objective: To rehabilitate power system of Zimbabwe ----------------- 2. Specific Objectives: Strengthening of transmission lines -------------------