P-Z1-DB0-182 Burkina Faso - Community Road Strengthening Project on CU2A : Gounghin-Fada N'Gourma - Piega – Niger Border Section

L’audit annuel de performance environnementale et sociale a pour objectif global d'évaluer le niveau de conformité du projet en matière de...
Les services prévus dans le cadre de ce contrat comprennent : la revue de l’étude d’Avant-projet détaillé (APD) des tronçons...
PPM - Burkina Faso - Projet de renforcement de la route communautaire Cu2a section Gounghin-Fada N'Gourma-Piega-Frontière du Niger (simplifié) - Cu2a...
Les services prévus au titre de ce contrat comprennent l’examen technique des travaux routiers du projet ci-dessus pour informer sur l’efficacité...

Project details

P-Z1-DB0-182 Ongoing

Burkina Faso - Community Road Strengthening Project on CU2A : Gounghin-Fada N'Gourma - Piega – Niger Border Section

Country
Multinational
Location
REGIONS DU CENTRE–EST ET DE L’EST
Sector
Transport
Task manager
YOUGBARE BarnabeRDGW3
Implementing agency
DIRECTION GENERALE DES INFRASTRUCTURES ROUTIERES (DGIR)
Appraisal
11-سبتمبر-2017
Board presentation
24-نوفمبر-2017
Approval
24-نوفمبر-2017
Implementation
27-يونيو-2019
Total cost182977400 UAC

Source(s) of financing

  • ACFA36360000
  • ADF41360000
  • AfDB35000000
  • Cofinanced48127400
  • Government22130000

Objectives

The sectoral objective of the project is to contribute to strengthening regional integration and the growth of intra-regional trade in the WAEMU zone. Its specific objectives are to improve the level of service of the road as well as the living conditions of the populations in the zone of intervention of the project (ZIP).

Description

This project was conceived as part of the West African Economic and Monetary Union (WAEMU) Commission Community Infrastructure and Road Transport Program (PACITR). It consists of the rehabilitation and asphalting of the Gounghin - Fada N'Gourma - Piéga - Niger border section of the national road no. 4 located on the CU2a community corridor of the UEMOA road network. The project was initiated due to the advanced state of degradation of the above-mentioned section. It is also a project falling within the first strategic axis of the accelerated growth and Sustainable Development Strategy (SCADD) which aims inter alia the construction and rehabilitation of road corridors, to facilitate the transport of people and goods, as well as the flow of production. The estimated total cost of the project is UA 162.21 million or EUR 204.39 million or CFAF 134.059 billion. The project consists of the following components: (i) road works; (ii) related activities; (iii) transport facilitation; (iv) support to the transport sector; and (v) project management.

Benefits

The direct beneficiaries of the project are the road users and the populations of the project area.