P-KE-FA0-027 Kenya - 35MW OrPower Menengai Geothermal Power Project

The Project involves design, construction, operation, and maintenance of a modular geothermal power plant with capacity of 35 MW in the Menengai...
OrPower Twenty-Two Limited (OTTL), the proponent, is desirous of constructing and operating 1X35MW geothermal power plant within Menengai geothermal...

Project details

P-KE-FA0-027 Approved

Kenya - 35MW OrPower Menengai Geothermal Power Project

Country
Kenya
Sector
Power
Approval
24-نوفمبر-2025

Source(s) of financing

    Objectives

    The project aims to increase Kenya’s supply of clean, reliable and affordable baseload electricity by developing 35 MW of geothermal generation capacity at Menengai.

    More specifically, it seeks to diversify Kenya’s energy mix, reduce reliance on electricity imports, meet growing national electricity demand, mobilize private investment in renewable energy, and support the country’s transition towards a fully clean electricity system. The project will also contribute to reducing greenhouse gas emissions and strengthening the resilience and security of Kenya’s power supply.

    Description

    The 35 MW OrPower Menengai Geothermal Power Project is a private-sector renewable energy project in Kenya involving the design, construction, operation and maintenance of a modular geothermal power plant in the Menengai geothermal field, Nakuru County, approximately 180 km northwest of Nairobi. The project also includes the construction of an on-site substation and a 500-metre transmission interconnector linking the plant to the Menengai substation.

    The project will be implemented under a Build, Own and Operate (BOO) model by OrPower Twenty-Two Limited (OTTL), a Kenyan special-purpose vehicle wholly owned by Kaishan Renewable Energy Limited. OTTL holds a 25-year take-or-pay Power Purchase Agreement with Kenya Power and Lighting Company (KPLC) and a Project Implementation and Steam Supply Agreement with the Geothermal Development Company (GDC).

    The total project cost is estimated at USD 91.9 million. Senior debt of up to USD 64.4 million is expected to be jointly provided by the African Development Bank and the International Finance Corporation, with IFC acting as mandated lead arranger. The African Development Bank will provide a senior secured loan of up to USD 16.5 million. The project complements the Bank’s earlier investment of USD 145 million in the development of the Menengai geothermal steam field.

    Benefits

    The project is located in the Menengai geothermal field in Nakuru County, Kenya, approximately 180 km northwest of Nairobi. The primary beneficiaries are electricity consumers throughout Kenya, including households, businesses, industries and public institutions, who will benefit from increased access to reliable, affordable and low-carbon electricity.

    Institutional and commercial beneficiaries include KPLC, which will purchase the electricity generated under the long-term power purchase agreement, and GDC, which will supply geothermal steam to the plant. The project will also support Kenya’s wider electricity sector by increasing installed green baseload capacity and reducing the need for electricity imports from neighbouring countries.