P-SZ-DB0-010 Eswatini - Mbabane Bypass Road

The principal objective of this combined assignment is to build sustainable, high-quality technical capacity within both beneficiary institutions...
The objective is to design and deliver a programme that equips staff with the skills and mindset for the transition to the ERA, Construction...
The Government of the Kingdom of Eswatini has received a Loan from the African Development Bank (AfDB) towards the cost of the Eswatini Road...
The objective of the Environmental & Social Audit Consultancy Services is to provide an independent, evidence-based assessment of the...
PPM - Eswatini - Eswatini Road Infrastructure Improvement Programme Phase 1 (Simplified)
The Consultancy services include but are not restricted to the following: Preliminary Services: Design review; Management of...
The Government of the Kingdom of Eswatini has received a Loan from the African Development Bank to finance Eswatini Road Infrastructure...
The objective of the Communication and Visibility Results for ERIIP Phase 1 is to develop and implement an effective and efficient communication...
PPM - Eswatini - Eswatini Road Infrastructure Improvement Programme Phase 1 - ERIIP

Project details

P-SZ-DB0-010 Completed

Eswatini - Mbabane Bypass Road

Country
Eswatini
Location
HHOHHO REGION
Sector
Transport
Task manager
GEBREMEDHIN DawitRDGS4
Implementing agency
MINISTRY OF WORKS - COMMUNICATIONS
Appraisal
30-أبريل-2003
Board presentation
17-ديسمبر-2003
Approval
17-ديسمبر-2003
Implementation
18-أغسطس-2004
Total cost40245998 UAC

Source(s) of financing

  • AfDB32449330.49
  • Government7795376.79

Objectives

2. Project Objective 2.1 To improve the quality of transport service levels and reduce vehicle operating costs on the Mbabane Bypass.

Description

The project comprises the following components: a) Upgrading 5-km of existing two-lane paved road and construction of 6-km road to 50-mm thick asphalt concrete dual carriageway (2x7.0-m lanes per direction) and 2.0-meter wide paved shoulder on each side of the Mbabane Bypass (total length 11 km); b) Consultant services for the supervision of the civil works; and c) Project audit services.

Benefits

The project road will represent upgrading from a two-lane to a four-lane dual carriage-way for the SCOT Junction-Nkoyoyo; and four-lane new alignment for SCOT Junction to downtown. Two types of benefits are relevant to upgrading of the road compared to the current situation of continuation of basic maintenance. These benefits are savings in road user costs and maintenance costs. The road user cost savings consists of difference in vehicle operating costs (VOC) related to both distance and time between the improved and existing road options. With regard to the road maintenance savings, the upgraded road entails much lower maintenance costs compared to a deteriorated and/or lower grade road surface that calls for constant attention in terms of maintenance. With regard to the Mbabane Bypass road, reductions in accident as well as congestion aspects were included in the calculation of benefits. The impact of congestion on VOC and hence on the economic analysis results was directly modeled by the Highway Design and Management Model (HDM IV). Potential benefits from reduced accidents resulting from the upgrading of the existing road to dual carriageway were computed as exogenous variable. A number of qualitative benefits will accrue to road users. The road users including the traveling public will benefit by reason of reduction in travel times which is normally associated with higher speeds as a result of upgrading of the road. The lower travel times will have the positive impact in reducing inventory levels of traders, suppliers as well as manufacturers found in along the corridor. Other benefits like increased comfort, reliability, frequency, accessibility of transport services would be gained by upgrading the road. Ultimately, these invariably create easy and comfortable access to places of work, markets , schools, health facilities and the economic and reliable transport service.

Rationale

A cardinal concept and rationale behind the initiation of the project and its design to a dual carriageway is to bring positive impacts in the form of enhancement to safety for vehicles and pedestrians as well as improve business/developmental opportunities in terms of the employment, convenience, and linkages to regional development. The proposed project fits within the Bank#s strategy and the framework of the Government#s transport policy to improve accessibility to industrial and agricultural settings and also to construct international roads thereby promoting regional integration and trade. The project is designed to assist a proportion of the population through increased access to markets and basic social services at lower costs, facilitate and improve traffic movements to and from the region, reduce vehicle operating costs and maintenance costs, stimulate the agricultural sector and introduce opportunities for economic growth. The existing Mbabane Bypass road, which is a two-lane road, is congested particularly with heavy vehicles. There is a need to upgrade the Bypass to a dual carriageway so as eliminate the transportation bottlenecks (such as congestion) currently experienced on the road. The Bypass will be upgraded to similar geometric standards like the contiguous sections between Nkoyoyo and Ngwenya, and between Mbabane and Manzini. The current design concept is for the carriageway and the shoulders to be of asphalt concrete surfacing. This will enable high traffic volumes along the project road to be catered for with a view to reduce congestion/queuing of vehicles and accidents. The dual carriageway will improve pedestrian, vehicle and livestock safety. The sealed carriageway provides a durable and smooth riding surface thereby lowering vehicle operating costs and maintenance costs and also minimizes moisture ingress into the pavement from surface runoff. Road furniture and ancillary structures (such as pedestrian footbridges bridges, bus bays, Grade Separated Interchanges - GSI, service roads to link to the GSIs, access roads rerouted to tie with GSIs, etc.) have been provided to enhance level of service and safety aspects on the Mbabane Bypass. The designs adopted for the dual carriageway comply with MPWT and also Southern Africa Transport and Communications Commission (SATCC) design standards for harmonization.