تقرير التقدم المحرز في التنفيذ والنتائج
L’objectif de développement du projet reste valable et est en bonne voie de réalisation. La mise en œuvre du RGA et la dynamisation de la...
Mission date: From 03/12/2019 To 13/12/2019
The project objectives are: (i) improve sustainable road access and quality of transport service...
12-أغسطس-2020
South Sudan - Resilient Water Project for Improved Livelihood In Juba (RWPILJ) - IPR April 2020
Mission date: 28/04/2020 29/04/2020
Most of the outcomes are likely to be achieved following the procurement of a new consultant. 3 3
12-أغسطس-2020
South Sudan - Gender Equality and Women’s Economic Empowerment for Inclusion - IPR December 2018
Mission date: N/A
The project has been challenged by a slow start further compounded with delays in the project implementation attributed to...
Mission date: From: 3/11/2019 To: 8/11/2019
It was discussed and agreed that a oneyear extension of the closing date of the Project was...
11-أغسطس-2020
Uganda - Multinational Lake Victoria Maritime Communication and Transport (MLVMCT) Project – IPR October 2019
Mission date: 19-23.08.2019
The implementation of progress is fair. The project has made considerable progress since December 2018. A total...
Mission date: From: 07/10/2019 To: 16/10/2019
All Outcomes are expected to be reached, and at present 90% of outputs re on track to reach...