Relatório de progresso na implementação e resultados
L’objectif de développement du projet reste valable et est en bonne voie de réalisation. La mise en œuvre du RGA et la dynamisation de la...
Mission date: From 03/12/2019 To 13/12/2019
The project objectives are: (i) improve sustainable road access and quality of transport service...
12-Ago-2020
South Sudan - Resilient Water Project for Improved Livelihood In Juba (RWPILJ) - IPR April 2020
Mission date: 28/04/2020 29/04/2020
Most of the outcomes are likely to be achieved following the procurement of a new consultant. 3 3
12-Ago-2020
South Sudan - Gender Equality and Women’s Economic Empowerment for Inclusion - IPR December 2018
Mission date: N/A
The project has been challenged by a slow start further compounded with delays in the project implementation attributed to...
Mission date: From: 3/11/2019 To: 8/11/2019
It was discussed and agreed that a oneyear extension of the closing date of the Project was...
Mission date: 19-23.08.2019
The implementation of progress is fair. The project has made considerable progress since December 2018. A total...