Vous êtes ici
Lesotho - Projet d'approvisionnement en électricité - Résumé PGES
Adverse Impacts: Distribution network systems extension can be expected to have minor direct and indirect impacts on villages and hamlets where the proposed lines pass. The potential for negative direct impacts might be in any social and cultural interaction between the contractor’s workers and local populations. There may also be minor effects on agriculture, if there would be a restriction on land use in the right of way to the areas where distribution lines pass, and, in any involuntary resettlement requirement. Issues addressed in the ESMP include tree cutting, local land degradation and soil erosion, aesthetics and visual impact and ecological issues. The sites for the sub-stations have been procured already by Lesotho Electricity Company (LEC) and are fenced of. No negative environmental impact is expected.