Lesotho - Khamane-Oxbow Road Project - PPER

15-Jan-2015

This Project Performance Evaluation Report (PPER) is concerned with the performance of the Khamane - Oxbow Road Project in Lesotho.

On 18 June 1986, ADF Loan Nº CS/LES/TR/86/18 in the amount of UA 6.424 million was approved by ADF for the Project. The loan was declared effective on 1 April 1987 and the first disbursement was made on 26 June 1987. The final completion of the works was on 10 April 1990 and the last disbursement was made on 22 September 1994. The Loan was used to finance the construction of the project road to bitumen standard, including construction supervision and contractor’s claim analysis by a consulting firm.